Yes, you can schedule reports to run quarterly, half yearly and yearly. Not all reports are provided with the quarterly, half-yearly, and yearly options. Only the following reports can be scheduled to run  quarterly, half-yearly, and yearly:

  • Trips ReportReport
  • Summary Report
  • Geofence Report
  • Speeding Report
  • Stop Time Report
  • Idling Report

To schedule reports to run quarterly, half yearly, or yearly:

1. Login to the Azuga application.

2. Navigate to the Scheduled page, under the Reports tab.

Qce0u8r1HwJfu_DXRGUz6CJOfZUZIEyjDQ.png


3. Select the report you wish to schedule from the drop-down and click the Schedule button.

TNtJy8VUz5pH9DIAcSWEXK8_0vF6b06kVw.png



4. Fill out the form with appropriate details.

Z4PvLJC2N2Fv7CtDGWeDyu5y9CwlL9O_aA.JPG


  • If you want to schedule the report quarterly, half yearly, or yearly, then click the corresponding radio button and set the date and time. 


5. Click the Schedule Report button.